Colonial Drive Enhancements (2019)
- Colonial Drive, Tuscaloosa, Alabama 35487
Use
Road
Status
Construction Type
Other
Current Phase
Complete
College or Division
Division of Finance and Operations
CA Filing Code
TRN-19-2159
Project GSF
NA
Bid Date
February 20, 2020
Construction Start
March 21, 2020
Construction End
July 19, 2020
Project Architect
McGiffert and Associates
General Contractor
John Plott Company, Inc.
Project Manager
Steven Mercado (8-4640)
Field Coordinator
TBD
Interior Designer
N/A
Project Admin
Brittney Fox
The Colonial Drive Enhancements project (“Project”) will entail the renovation of the existing Colonial Drive between University Boulevard and Bryant Drive. This proposed Project will help alleviate traffic congestion in the heart of campus and improve the quality and character of the area. The Project will allow for the elimination of bus traffic on Bryant Drive and provide an express route from the south residential area to the core of campus. By reducing traffic in this area, it will also reduce the potential for pedestrian and vehicle conflicts creating a safer pedestrian environment.
The proposed Project will allow for bus and bike traffic to go in both the north and south direction and standard vehicle traffic to continue in the south bound direction. Increased street and pedestrian lighting will provide a safer path of travel for the pedestrians in evening hours. A new valley gutter will also be installed along the west side of the street to allow for better pedestrian access to the stadium on game days. The Project pavement profile will be built to accommodate Crimson Ride transit System buses.
The project will also include the installation of both static and operable impact resistant bollards at the Colonial Drive and Bryant Drive intersection in accordance with the Bryant-Denny Stadium Gameday Security plan. Operable bollards at the intersection will allow for the elimination of large vehicles that are used as barriers on Gameday. This will greatly enhance pedestrian flow in the area.
This Project will include all necessary support infrastructure including security and safety equipment, lighting, and landscaping.
BOT Budget
$3,750,000.00
Funding Sources
-
University Plant Reserves :
$3,750,000
Banner/Project #
90890
Project Accountant
Demon Patrick (8-8714)
STAGE | PACKAGE INFORMATION |
---|---|
Stage 1 |
|
Stage 2 |
|
Stage 3 |
|
Stage 4 |
|
Bid Package | Important Dates | Bid Documents | |
---|---|---|---|
Construction Package | Prequalifications Due:
January 21, 2020 5:00 pm Mandatory Pre-bid Conference: January 30, 2020 2:00 pm Mandatory Pre-bid Conference Location: Procurement Services Annex Bid Opening: February 11, 2020 2:00 pm Bid Opening Location: Procurement Services Annex |
||
DATA LABEL | DATA VALUE |
---|---|
Category | Road |
College/Division | Division of Finance and Operations |
Parking Spaces | |
Status | Active |
Construction Phase | Complete |
Construction Type | Other |
GSF | NA |
Street Address | Colonial Drive, Tuscaloosa, Alabama 35487 |
Zone | |
Project Number | TRN-19-2159 |
Architect | McGiffert and Associates |
Project Manager | Steven Mercado (8-4640) |
Project Admin | Brittney Fox |
Field Coordinator | TBD |
General Contractor | John Plott Company, Inc. |
Interior Designer | N/A |
Bid Date | February 20, 2020 |
Construction Start | March 21, 2020 |
Scheduled Construction End | July 19, 2020 |
SharePoint Active Project Site Link | https://uafinancialaffairs.sharepoint.com/sites/9VD1V/LAN-19-2159/ |
AiM Link | https://fmax.fa.ua.edu/fmax/screen/PROJECT_VIEW?project=90890 |
Campus Map Link | https://map.concept3d.com/?id=1222#!m/436359 |
BIR Building Link | https://uafinancialaffairs.sharepoint.com/sites/98C3D/default.aspx |
Construction Photos Link | |
Project Summary |
The Colonial Drive Enhancements project (“Project”) will entail the renovation of the existing Colonial Drive between University Boulevard and Bryant Drive. This proposed Project will help alleviate traffic congestion in the heart of campus and improve the quality and character of the area. The Project will allow for the elimination of bus traffic on Bryant Drive and provide an express route from the south residential area to the core of campus. By reducing traffic in this area, it will also reduce the potential for pedestrian and vehicle conflicts creating a safer pedestrian environment. The proposed Project will allow for bus and bike traffic to go in both the north and south direction and standard vehicle traffic to continue in the south bound direction. Increased street and pedestrian lighting will provide a safer path of travel for the pedestrians in evening hours. A new valley gutter will also be installed along the west side of the street to allow for better pedestrian access to the stadium on game days. The Project pavement profile will be built to accommodate Crimson Ride transit System buses. The project will also include the installation of both static and operable impact resistant bollards at the Colonial Drive and Bryant Drive intersection in accordance with the Bryant-Denny Stadium Gameday Security plan. Operable bollards at the intersection will allow for the elimination of large vehicles that are used as barriers on Gameday. This will greatly enhance pedestrian flow in the area. This Project will include all necessary support infrastructure including security and safety equipment, lighting, and landscaping. |
Renderings | |
Budget | 3750000 |
Banner Fund Number | 90890 |
Project Accountant | Demon Patrick (8-8714) |
Funding Source 1 | |
Funding Source 1 Amount | |
Funding Source 2 | |
Funding Source 2 Amount | |
Funding Source 3 | |
Funding Source 3 Amount | |
Funding Source 4 | |
Funding Source 4 Amount | |
ePIRPAF Link | https://everest-sf.fa.ua.edu/Runtime/Form/Project%20Initiation%20Request/?_State=PIR_HISTORY&GUID=C05417D1-288A-44BB-81CA-A939E8A2534E |
Construction Dashboard Link | https://spd.ua.edu/construction/Awards/Funds?fund=90890&detail=all |
View Bid Tab | https://constructionpublicinfo.ua.edu/certified-bid-tabs/ |
Link to eCORAF | https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList |
Link to ePayApp | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard |
BOT Stage I | September 2019 |
BOT Stage II | September 2019 (W) |
BOT Stage III | TBD |
BOT Stage IV | TBD |
Attachment I | |
Stage 1 Submittal PDF | |
Stage 2 Submittal PDF | |
CSP I PDF | |
CSP II PDF | |
Stage 3 Submittal PDF | |
Stage 4 Submittal PDF | |
BOT Info Item PDF | |
BOT Site | https://uafinancialaffairs.sharepoint.com/sites/6JDXH/BOTProjects/BOT-205/ |
COSC Date | |
Year End Inspection | |
View Warranty Documents | |
Stage 1 BOT Submittal(s) | |
Stage 2 BOT Submittal(s) | |
Stage 3 BOT Submittal(s) | |
Stage 4 BOT Submittal(s) | |
Funding Source(s) | |
Fundraising Site | |
Link to Awarded Contracts Dashboard | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard |
Closeout Documents Link | |
RFQ Documents | |
Advertisement for Bids | |
Bid Tabulations | |
Link to Bid Site | https://constructionpublicinfo.ua.edu/bids/ |
Consultant Agreements | https://constructionpublicinfo.ua.edu/agreements/ |
Design Guidelines | https://constructionpublicinfo.ua.edu/design-guidelines/ |
Front End Documents | https://constructionpublicinfo.ua.edu/front-end-documents/ |
Instructions Link | https://constructionpublicinfo.ua.edu/public-forms/ |
360 Embed Code |