Angelo Bruno Business Library Renovation

  • 425 Stadium Drive
Information at a Glance

Use

Academic

Status

Hold

Construction Type

Renovation

Current Phase

Design

College or Division

College of Business

CA Filing Code

036-19-2003

Project GSF

31,415

Bid Date

TBD

Construction Start

TBD

Construction End

Summer 2022

Project Architect

B Group Architecture

General Contractor

TBD

Project Manager

Terrence Craven (8-8698)

Field Coordinator

TBD

Interior Designer

Brittany Kyles (8-9001)

Project Admin

Brittney Fox

Project Summary

This project is a critical step in the realignment of library space necessary to meet the strategic plan of The University of Alabama and to transform the UA libraries as necessary to support the academic mission and the teaching, research and learning environment in the 21st Century.

The project will consist of the renovation and reorganization of the first-floor space of approximately 22,165 GSF, and the renovation of the ground floor where the Bashinsky Computer Lab and roughly 9,250 GSF of office space are located. The project will provide additional open, collaborative, small group study spaces in the library, and update the computer lab with furniture to promote student group study activities. The building originally opened in 1994 and the furniture and finishes are original to the building an in need of replacement. Modifications to the existing mechanical, electrical and life safety systems will be completed as necessary. Upgrades to the network will be made to support wireless demands for the additional students in the spaces. There will be no exterior modifications to the building.


Information at a Glance

BOT Budget

$3,527,175.00

Funding Sources

  • Office of Academic Affairs Reserves:
    $2,500,000
  • Bashinsky Computer Support Fund:
    $600,000
  • University Plant Reserves:
    $427,175

Banner/Project #

90891

Project Accountant

Demon Patrick (8-8714)

BOT Submissions
STAGE PACKAGE INFORMATION

Stage 1

Stage 2

Stage 3

Stage 4

DATA LABEL DATA VALUE
Category Academic
College/Division College of Business
Parking Spaces
Status Hold
Construction Phase Design
Construction Type Renovation
GSF 31,415
Street Address 425 Stadium Drive
Zone 1
Project Number 036-19-2003
Architect B Group Architecture
Project Manager Terrence Craven (8-8698)
Project Admin Brittney Fox
Field Coordinator TBD
General Contractor TBD
Interior Designer Brittany Kyles (8-9001)
Bid Date TBD
Construction Start TBD
Scheduled Construction End Summer 2022
SharePoint Active Project Site Link https://bama365.sharepoint.com/sites/9VD1V/036-19-2189/SitePages/Home.aspx
AiM Link https://fmax.fa.ua.edu/fmax/screen/PROJECT_VIEW?project=90891
Campus Map Link https://map.concept3d.com/?id=1222#!m/436360
BIR Building Link https://bama365.sharepoint.com/sites/98C3D/Zone1/buildings/036/default.aspx
Construction Photos Link https://uafinancialaffairs.sharepoint.com/sites/7M27T/219-18-1324/Close%20Out%20Documents/Forms/AllItems.aspx
Project Summary

This project is a critical step in the realignment of library space necessary to meet the strategic plan of The University of Alabama and to transform the UA libraries as necessary to support the academic mission and the teaching, research and learning environment in the 21st Century.

The project will consist of the renovation and reorganization of the first-floor space of approximately 22,165 GSF, and the renovation of the ground floor where the Bashinsky Computer Lab and roughly 9,250 GSF of office space are located. The project will provide additional open, collaborative, small group study spaces in the library, and update the computer lab with furniture to promote student group study activities. The building originally opened in 1994 and the furniture and finishes are original to the building an in need of replacement. Modifications to the existing mechanical, electrical and life safety systems will be completed as necessary. Upgrades to the network will be made to support wireless demands for the additional students in the spaces. There will be no exterior modifications to the building.

Renderings Array
Budget 3527175
Banner Fund Number 90891
Project Accountant Demon Patrick (8-8714)
Funding Source 1
Funding Source 1 Amount
Funding Source 2
Funding Source 2 Amount
Funding Source 3
Funding Source 3 Amount
Funding Source 4
Funding Source 4 Amount
ePIRPAF Link https://everest-sf.fa.ua.edu/Runtime/Form/Project%20Initiation%20Request/?_State=PIR_HISTORY&GUID=D558321B-5E88-443C-B02E-8D18475259B4
Construction Dashboard Link https://spd.ua.edu/construction/Awards/Funds?fund=90891&detail=all
View Bid Tab
Link to eCORAF https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList
Link to ePayApp https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard
BOT Stage I September 2019
BOT Stage II TBD
BOT Stage III TBD
BOT Stage IV TBD
Attachment I
Stage 1 Submittal PDF Array
Stage 2 Submittal PDF
CSP I PDF
CSP II PDF
Stage 3 Submittal PDF
Stage 4 Submittal PDF
BOT Info Item PDF
BOT Site https://uafinancialaffairs.sharepoint.com/sites/6JDXH/BOTProjects/BOT-191/
COSC Date
Year End Inspection
View Warranty Documents
Stage 1 BOT Submittal(s) Array
Stage 2 BOT Submittal(s) Array
Stage 3 BOT Submittal(s)
Stage 4 BOT Submittal(s)
Funding Source(s) Array
Fundraising Site
Link to Awarded Contracts Dashboard https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard
Link to Bid Site https://constructionpublicinfo.ua.edu/bids/
Consultant Agreements https://constructionpublicinfo.ua.edu/agreements/
Design Guidelines https://constructionpublicinfo.ua.edu/design-guidelines/
Front End Documents https://constructionpublicinfo.ua.edu/front-end-documents/
Instructions Link https://constructionpublicinfo.ua.edu/public-forms/
Advertisement for Bids
RFQ Documents Array
Bid Tabulations
Closeout Documents Link
360 Embed Code