McLure Library Addition and Renovation
- 918 University Boulevard
Use
Academic
Status
Construction Type
Addition
Current Phase
Design
College or Division
University Libraries
CA Filing Code
051-23-2688
Project GSF
29,137
Bid Date
February 20, 2024
Construction Start
Summer 2024
Construction End
May 2025
Project Architect
KPS Group
General Contractor
WAR Construction Inc.
Project Manager
Mary Kathryn Holt
Field Coordinator
Colby Mixon
Project Admin
Katie Crocker-Buta
The proposed McLure Library Addition and Renovation project will allow for the relocation of the School of Library and Information Sciences from the 7th floor of Gorgas Library to McLure in accordance with the Gorgas Library Master Plan. SLIS is part of the College of Communications and Information Sciences, and this relocation will enhance program adjacency to Reese Phifer Hall and provide additional space needed in Gorgas while maintaining the College of Education programs within the space.
McLure Library was originally constructed in 1925 and renovated in 1954 for the College of Education Library. The building has remained primarily unchanged since that time and the Project will allow for the comprehensive renovation of McLure and will fully address all deferred maintenance issues including all new mechanical, electrical, accessibility, life safety systems, technology and building envelope issues including new windows.
The existing character, detailing and quality of the building is appropriate and much in keeping with campus and the building features standard University materials including brick and solid limestone columns, cornice and window surrounds. Together with Autherine Lucy Hall, the buildings have complemented each other and been a part of the University Boulevard streetscape
for almost a century.
The addition will also provide space for code-required vertical circulation and an elevator as the building does not currently have one.
ADA access to McLure will be improved through the construction of a new entrance structure, which will also house program space below. Adjacent to the new entry will be a plaza and gathering space designed with brick pavers, precast seat walls, new landscaping, and site lighting.
The existing access plaza to the front of the building from University Boulevard will also be reconstructed as it has exceeded its service life and does not meet current structural code.
The Project will allow for the conversion of the stack space to general use and the floors will be aligned with the main building floors. The addition will not impact the University Boulevard elevation to maintain the character of the original building main elevation.
BOT Budget
$18,856,402.00
Funding Sources
-
University Central Reserves :
$18,856,402
Banner/Project #
91209
Project Accountant
Parker Christian
STAGE | PACKAGE INFORMATION |
---|---|
Stage 1 |
|
Stage 2 |
|
Stage 3 |
|
Stage 4 |
|
DATA LABEL | DATA VALUE |
---|---|
Category | Academic |
College/Division | University Libraries |
Status | Active |
Construction Phase | Design |
Construction Type | Addition |
GSF | 29,137 |
Street Address | 918 University Boulevard |
Zone | 1 |
Project Number | 051-23-2688 |
Architect | KPS Group |
Project Manager | Mary Kathryn Holt |
Project Admin | Katie Crocker-Buta |
Field Coordinator | Colby Mixon |
General Contractor | WAR Construction Inc. |
Interior Designer | |
Bid Date | February 20, 2024 |
Construction Start | Summer 2024 |
Scheduled Construction End | May 2025 |
COSC Date | |
Year End Inspection | |
Fundraising Site | |
SharePoint Active Project Site Link | https://bama365.sharepoint.com/sites/9VD1V/051-23-2688/SitePages/Home.aspx |
AiM Link | https://fmax.fa.ua.edu/fmax/screen/PROJECT_VIEW?project=91209 |
Campus Map Link | https://map.concept3d.com/?id=1222#!m/834458 |
BIR Building Link | https://bama365.sharepoint.com/sites/98C3D/default.aspx |
Closeout Documents Link | |
View Warranty Documents | |
Project Summary |
The proposed McLure Library Addition and Renovation project will allow for the relocation of the School of Library and Information Sciences from the 7th floor of Gorgas Library to McLure in accordance with the Gorgas Library Master Plan. SLIS is part of the College of Communications and Information Sciences, and this relocation will enhance program adjacency to Reese Phifer Hall and provide additional space needed in Gorgas while maintaining the College of Education programs within the space. McLure Library was originally constructed in 1925 and renovated in 1954 for the College of Education Library. The building has remained primarily unchanged since that time and the Project will allow for the comprehensive renovation of McLure and will fully address all deferred maintenance issues including all new mechanical, electrical, accessibility, life safety systems, technology and building envelope issues including new windows. The existing character, detailing and quality of the building is appropriate and much in keeping with campus and the building features standard University materials including brick and solid limestone columns, cornice and window surrounds. Together with Autherine Lucy Hall, the buildings have complemented each other and been a part of the University Boulevard streetscape The addition will also provide space for code-required vertical circulation and an elevator as the building does not currently have one. ADA access to McLure will be improved through the construction of a new entrance structure, which will also house program space below. Adjacent to the new entry will be a plaza and gathering space designed with brick pavers, precast seat walls, new landscaping, and site lighting. The existing access plaza to the front of the building from University Boulevard will also be reconstructed as it has exceeded its service life and does not meet current structural code. The Project will allow for the conversion of the stack space to general use and the floors will be aligned with the main building floors. The addition will not impact the University Boulevard elevation to maintain the character of the original building main elevation. |
Renderings | |
Budget | 18856402 |
Banner Fund Number | 91209 |
Project Accountant | Parker Christian |
Funding Source(s) | |
Construction Dashboard Link | |
Link to Awarded Contracts Dashboard | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard |
View Bid Tab | https://constructionpublicinfo.ua.edu/certified-bid-tabs/ |
Link to eCORAF | https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList |
Link to ePayApp | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard |
ePIRPAF Link | |
Stage 1 BOT Submittal(s) | |
Stage 2 BOT Submittal(s) | |
Stage 3 BOT Submittal(s) | |
Stage 4 BOT Submittal(s) | |
BOT Site | |
RFQ Documents | |
Advertisement for Bids | |
Bid Tabulations | |
Link to Bid Site | https://constructionpublicinfo.ua.edu/bids/ |
Consultant Agreements | https://constructionpublicinfo.ua.edu/agreements/ |
Design Guidelines | https://constructionpublicinfo.ua.edu/design-guidelines/ |
Front End Documents | https://constructionpublicinfo.ua.edu/front-end-documents/ |
Instructions Link | https://constructionpublicinfo.ua.edu/public-forms/ |
360 Embed Code | |
BOT Stage |