RISE Center Playscape Renovations & Enhancements
- 600 Johnny Stallings Dr
Use
Other
Status
Construction Type
Renovation
Current Phase
Design
College or Division
College of Human and Environmental Sciences
CA Filing Code
017-24-3587
Project GSF
22,000
Project Architect
HNP Landscape Architecture
Project Manager
Leila Ahmady
The RISE Center Playscape Renovations & Enhancements Project (“Project”) is a full overhaul of the existing playground areas at the RISE Center and is necessary to continue to fulfill the center’s mission of a blended learning environment where all kids shine. The current playground is not 100% accessible for all of the children at RISE, and this project will provide an opportunity for a state-of-the-art space for our children to thrive but to also be a model program for the Country when it comes to true accessibility for all levels of ability.
This Project will include therapeutic, fully accessible infant, toddler and preschool yards for the children and additional landscaping.
The Project is key to enhancing the experience of the children and their families of the center.
The Project will also address drainage issues in the exterior playground areas.
Advancement and the College will pursue funds for both the overall Project and the individual playscape components as illustrated in the construction packages included in the Total Project Budget above. The University will execute on the Project either as individual packages or comprehensively in conjunction with realized fundraising.
All Construction Packages include the associated playscape equipment as it will be installed integral with the work and will be included in the related package bids.
BOT Budget
$3,000,000.00
Funding Sources
-
Future Gifts :
$2,400,000 -
Office of Academic Affairs Reserve :
$600,000
Banner/Project #
99086
STAGE | PACKAGE INFORMATION |
---|---|
Stage 1 |
|
Stage 2 |
|
Stage 3 |
|
Stage 4 |
|
DATA LABEL | DATA VALUE |
---|---|
Category | Other |
College/Division | College of Human and Environmental Sciences |
Status | Fundraising |
Construction Phase | Design |
Construction Type | Renovation |
GSF | 22,000 |
Street Address | 600 Johnny Stallings Dr |
Zone | |
Project Number | 017-24-3587 |
Architect | HNP Landscape Architecture |
Project Manager | Leila Ahmady |
Project Admin | |
Field Coordinator | |
General Contractor | |
Interior Designer | |
Bid Date | |
Construction Start | |
Scheduled Construction End | |
COSC Date | |
Year End Inspection | |
Fundraising Site | |
SharePoint Active Project Site Link | https://bama365.sharepoint.com/sites/9VD1V/017-24-3587 |
AiM Link | https://fmax.fa.ua.edu/fmax/screen/PROJECT_VIEW?project=99086 |
Campus Map Link | |
BIR Building Link | https://bama365.sharepoint.com/sites/98C3D/default.aspx |
Closeout Documents Link | |
View Warranty Documents | |
Project Summary |
The RISE Center Playscape Renovations & Enhancements Project (“Project”) is a full overhaul of the existing playground areas at the RISE Center and is necessary to continue to fulfill the center’s mission of a blended learning environment where all kids shine. The current playground is not 100% accessible for all of the children at RISE, and this project will provide an opportunity for a state-of-the-art space for our children to thrive but to also be a model program for the Country when it comes to true accessibility for all levels of ability. This Project will include therapeutic, fully accessible infant, toddler and preschool yards for the children and additional landscaping. The Project is key to enhancing the experience of the children and their families of the center. The Project will also address drainage issues in the exterior playground areas. Advancement and the College will pursue funds for both the overall Project and the individual playscape components as illustrated in the construction packages included in the Total Project Budget above. The University will execute on the Project either as individual packages or comprehensively in conjunction with realized fundraising. All Construction Packages include the associated playscape equipment as it will be installed integral with the work and will be included in the related package bids. |
Renderings | |
Budget | 3000000 |
Banner Fund Number | 99086 |
Project Accountant | |
Funding Source(s) | |
Construction Dashboard Link | |
Link to Awarded Contracts Dashboard | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard |
View Bid Tab | https://constructionpublicinfo.ua.edu/certified-bid-tabs/ |
Link to eCORAF | https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList |
Link to ePayApp | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard |
ePIRPAF Link | |
Stage 1 BOT Submittal(s) | |
Stage 2 BOT Submittal(s) | |
Stage 3 BOT Submittal(s) | |
Stage 4 BOT Submittal(s) | |
BOT Site | |
RFQ Documents | |
Advertisement for Bids | |
Bid Tabulations | |
Link to Bid Site | https://constructionpublicinfo.ua.edu/bids/ |
Consultant Agreements | https://constructionpublicinfo.ua.edu/agreements/ |
Design Guidelines | https://constructionpublicinfo.ua.edu/design-guidelines/ |
Front End Documents | https://constructionpublicinfo.ua.edu/front-end-documents/ |
Instructions Link | https://constructionpublicinfo.ua.edu/public-forms/ |
360 Embed Code | |
BOT Stage |