Parker-Haun Tennis Facility
- 550 Peter Bryce Boulevard
Information at a Glance
Use
Athletics
Status
Construction Type
New Construction
Current Phase
Closeout
College or Division
Other
CA Filing Code
394-18-1686
Project GSF
5,407
Bid Date
February 4, 2021
Construction Start
February 22, 2021
Construction End
August 2021
COSC Date
' August 20, 2021
Project Architect
Ellis Architects
General Contractor
Snow-Blakeney Construction, Inc.
Project Manager
Paul Davis (8-2037)
Field Coordinator
Ed Sawyer
Interior Designer
Leah Shepherd
Information at a Glance
BOT Budget
$990,000
Funding Sources
Banner/Project #
90836
Project Accountant
DeMon Patrick
Request for Qualifications
Bid Information
DATA LABEL | DATA VALUE |
---|---|
Category | Athletics |
College/Division | Other |
Status | Closed |
Construction Phase | Closeout |
Construction Type | New Construction |
GSF | 5,407 |
Street Address | 550 Peter Bryce Boulevard |
Zone | |
Project Number | 394-18-1686 |
Architect | Ellis Architects |
Project Manager | Paul Davis (8-2037) |
Project Admin | |
Field Coordinator | Ed Sawyer |
General Contractor | Snow-Blakeney Construction, Inc. |
Interior Designer | Leah Shepherd |
Bid Date | February 4, 2021 |
Construction Start | February 22, 2021 |
Scheduled Construction End | August 2021 |
COSC Date | August 20, 2021 |
Year End Inspection | Information Not Yet Available |
Fundraising Site | |
SharePoint Active Project Site Link | https://bama365.sharepoint.com/sites/7M27T/394-18-1686/SitePages/Home.aspx |
AiM Link | https://fmax.fa.ua.edu/fmax/screen/PROJECT_VIEW?project=90836 |
Campus Map Link | https://map.concept3d.com/?id=1222#!m/561912 |
BIR Building Link | |
Closeout Documents Link | |
View Warranty Documents | |
Project Summary | |
Renderings | |
Budget | 990000 |
Banner Fund Number | 90836 |
Project Accountant | DeMon Patrick |
Funding Source(s) | |
Construction Dashboard Link | |
Link to Awarded Contracts Dashboard | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard |
View Bid Tab | https://constructionpublicinfo.ua.edu/certified-bid-tabs/ |
Link to eCORAF | https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList |
Link to ePayApp | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard |
ePIRPAF Link | |
Stage 1 BOT Submittal(s) | |
Stage 2 BOT Submittal(s) | |
Stage 3 BOT Submittal(s) | |
Stage 4 BOT Submittal(s) | |
BOT Site | |
RFQ Documents | |
Advertisement for Bids | |
Bid Tabulations | |
Link to Bid Site | https://constructionpublicinfo.ua.edu/bids/ |
Consultant Agreements | https://constructionpublicinfo.ua.edu/agreements/ |
Design Guidelines | https://constructionpublicinfo.ua.edu/design-guidelines/ |
Front End Documents | https://constructionpublicinfo.ua.edu/front-end-documents/ |
Instructions Link | https://constructionpublicinfo.ua.edu/public-forms/ |
360 Embed Code |