Math and Science Education Building Renovation

  • 411 Hackberry Lane, Tuscaloosa, Alabama 35487
Information at a Glance

Use

Academic

Status

Active

Construction Type

Renovation

Current Phase

Complete

College or Division

College of Arts and Sciences

CA Filing Code

034-19-2011

Project GSF

95,635

Bid Date

January 7, 2020

Construction Start

November 2019

Construction End

January 2021

COSC Date

' December 12, 2020

Project Architect

KPS Group, Inc.

General Contractor

J. T. Harrison Construction*

Project Manager

Mason Milner / Joshua Bollinger

Field Coordinator

Ed Sawyer (8-1684)

Interior Designer

Michael Hand (8-8456)

Project Admin

Samantha Woods

Project Summary

This project will involve the renovation of the main building as well as improvements to the Auditorium. Most of the project will focus on the interior of the building; however, the windows will be replaced and the openings will be reworks to be more consistent with campus architecture.

This project will support the relocation of the Math Technology Learning Center (MTLC) and will accommodate introductory laboratories for Physics, Astronomy, Geography, Geology, and New College.

The 3rd and 4th floors will be repurposed to accommodate the MTLC, made necessary by the demolition of the Tutwiler Annex, which is the MTLC’s current location.

New spaces will accommodate a studio format, which integrates lectures and labs for a more efficient and valuable academic experience.


Information at a Glance

BOT Budget

$25,148,051.00

Funding Sources

  • 2019 General Revenue Bonds :
    $25,148,051

Banner/Project #

90838

Project Accountant

Sherell Harrison (8-6838)

DATA LABEL DATA VALUE
Category Academic
Status Active
Construction Phase Complete
Construction Type Renovation
GSF 95,635
Bid Date January 7, 2020
Project Number 034-19-2011
Architect KPS Group, Inc.
Project Manager Mason Milner / Joshua Bollinger
General Contractor J. T. Harrison Construction*
Project Summary

This project will involve the renovation of the main building as well as improvements to the Auditorium. Most of the project will focus on the interior of the building; however, the windows will be replaced and the openings will be reworks to be more consistent with campus architecture.

This project will support the relocation of the Math Technology Learning Center (MTLC) and will accommodate introductory laboratories for Physics, Astronomy, Geography, Geology, and New College.

The 3rd and 4th floors will be repurposed to accommodate the MTLC, made necessary by the demolition of the Tutwiler Annex, which is the MTLC’s current location.

New spaces will accommodate a studio format, which integrates lectures and labs for a more efficient and valuable academic experience.

Renderings
SharePoint Active Project Site Link https://bama365.sharepoint.com/sites/9VD1V/034-19-2011/SitePages/Home.aspx
Campus Map Link https://map.concept3d.com/?id=1222#!m/416113
BIR Building Link https://uafinancialaffairs.sharepoint.com/sites/98C3D/Zone1/buildings/034
Budget 25148051
Banner Fund Number 90838
Project Accountant Sherell Harrison (8-6838)
Funding Source 1
Funding Source 1 Amount
Funding Source 2
Funding Source 2 Amount
Funding Source 3
Funding Source 3 Amount
Funding Source 4
Funding Source 4 Amount
ePIRPAF Link https://everest-sf.fa.ua.edu/Runtime/Form/Project%20Initiation%20Request/?_State=PIR_HISTORY&GUID=00FE5DDC-CD66-4618-BD50-B532D4C4BE6F
Construction Dashboard Link https://spd.ua.edu/construction/Awards/Funds?fund=90838&detail=all
BOT Stage I April 2019
BOT Stage II June 2019
BOT Stage III September 2019
BOT Stage IV November 2019
Stage 1 Submittal PDF
Stage 2 Submittal PDF
Stage 3 Submittal PDF
Stage 4 Submittal PDF
BOT Site https://uafinancialaffairs.sharepoint.com/sites/6JDXH/BOTProjects/BOT-193/
Zone
Street Address 411 Hackberry Lane, Tuscaloosa, Alabama 35487
View Bid Tab
Construction Start November 2019
Scheduled Construction End January 2021
College/Division College of Arts and Sciences
Project Admin Samantha Woods
Field Coordinator Ed Sawyer (8-1684)
AiM Link https://fmax.fa.ua.edu/fmax/screen/PROJECT_VIEW?project=90838
COSC Date December 12, 2020
Year End Inspection TBD
View Warranty Documents
Parking Spaces
Interior Designer Michael Hand (8-8456)
Construction Photos Link
Link to eCORAF https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList
Link to ePayApp https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard
Attachment I
CSP I PDF
CSP II PDF
BOT Info Item PDF
Stage 1 Package Fields
Funding Source(s)
Stage 1 BOT Submittal(s)
Stage 2 BOT Submittal(s)
Stage 3 BOT Submittal(s)
Stage 4 BOT Submittal(s)
Fundraising Site
Link to Awarded Contracts Dashboard https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard
Link to Bid Site https://constructionpublicinfo.ua.edu/bid/bid-opening-math-science-education-building-renovation-pkg-b-034-19-2011b/
Consultant Agreements https://constructionpublicinfo.ua.edu/agreements/
Design Guidelines https://constructionpublicinfo.ua.edu/design-guidelines/
Front End Documents https://constructionpublicinfo.ua.edu/front-end-documents/
Instructions Link https://constructionpublicinfo.ua.edu/public-forms/
Advertisement for Bids
Closeout Documents Link
RFQ Documents
Bid Tabulations
360 Embed Code