Greek Assembly Hall

  • Campus Drive East
Information at a Glance

Use

Public Safety

Status

Closed

Construction Type

New Construction

Current Phase

Complete

College or Division

Other

CA Filing Code

356-21-2318

Project GSF

13,757

Bid Date

March 1, 2022

Construction Start

April 11, 2022

Construction End

July 2023

Project Architect

Adams Stewart Architecture, LLC

General Contractor

J.T. Harrison Construction Co., Inc.

Project Manager

Leila Ahmady (8-7241)

Field Coordinator

Chuck Hinton

Project Admin

Alison Langham

Project Summary

The Greek Assembly Hall is an approximately 12,671 gross square foot multipurpose safe shelter suitable to accommodate 1,000 occupants during severe weather events and designed to be flexible for group sizes and needs and will include spaces with operable partitions which can be easily adjusted for events, meetings and study groups. Its primary use and purpose is a Tornado Safe Shelter, designed in accordance with the requirements of FEMA 361 and International Code Council (ICC) 500.

The Greek Assembly Hall will be programmed for priority use by National Pan-Hellenic Council (NPHC) and Alabama United Greek Council (UGC) chapters for meetings, events, study groups and other uses during non-storm periods. Adjoined the building is the NPHC plaza, that honors The National Pan-Hellenic Council (NPHC) which is the coordinating council for the nine historically African American Greek-letter organizations, often referred to as the Divine Nine. This plaza includes monuments showcasing each of the nine organizations’ crests and their Greek letters.

Located on Campus Drive East between the Recreation Center (Rec) and Bryce Lawn Apartments, the Project serves the overall east-central campus area as there is a high density of students in the area and in the surrounding housing complexes and fraternity houses along University Boulevard, Bryce Lawn Drive and Jefferson Avenue. The Project also provides quick access for users of the Rec Fields during other inclement weather events.

 

View Progress Photos!
Information at a Glance

BOT Budget

$9,793,825.00

Funding Sources

  • Federal Emergency Management Administration-Pre-Disaster Mitigation Grant Program:
    $3,565,669
  • University Central Reserves:
    $6,092,302

Banner/Project #

90944

Project Accountant

Cindy Fowler

BOT Submissions
STAGE PACKAGE INFORMATION

Stage 1

Stage 2


Stage 3

Stage 4

View Board Manual
DATA LABEL DATA VALUE
Category Public Safety
College/Division Other
Status Closed
Construction Phase Complete
Construction Type New Construction
GSF 13,757
Street Address Campus Drive East
Zone 4
Project Number 356-21-2318
Architect Adams Stewart Architecture, LLC
Project Manager Leila Ahmady (8-7241)
Project Admin Alison Langham
Field Coordinator Chuck Hinton
General Contractor J.T. Harrison Construction Co., Inc.
Interior Designer
Bid Date March 1, 2022
Construction Start April 11, 2022
Scheduled Construction End July 2023
COSC Date
Year End Inspection Information Not Yet Available
Fundraising Site
SharePoint Active Project Site Link https://bama365.sharepoint.com/sites/9VD1V/356-21-2318
AiM Link https://fmax.fa.ua.edu/fmax/screen/WO_VIEW?proposal=90944
Campus Map Link https://map.concept3d.com/?id=1222#!m/576102?ce/31890?bm/?ct/40824,31490?mc/33.21292070361906,-87.5374746322632?z/16?lvl/0
BIR Building Link https://bama365.sharepoint.com/sites/98C3D/default.aspx
Closeout Documents Link
View Warranty Documents
Project Summary

The Greek Assembly Hall is an approximately 12,671 gross square foot multipurpose safe shelter suitable to accommodate 1,000 occupants during severe weather events and designed to be flexible for group sizes and needs and will include spaces with operable partitions which can be easily adjusted for events, meetings and study groups. Its primary use and purpose is a Tornado Safe Shelter, designed in accordance with the requirements of FEMA 361 and International Code Council (ICC) 500.

The Greek Assembly Hall will be programmed for priority use by National Pan-Hellenic Council (NPHC) and Alabama United Greek Council (UGC) chapters for meetings, events, study groups and other uses during non-storm periods. Adjoined the building is the NPHC plaza, that honors The National Pan-Hellenic Council (NPHC) which is the coordinating council for the nine historically African American Greek-letter organizations, often referred to as the Divine Nine. This plaza includes monuments showcasing each of the nine organizations’ crests and their Greek letters.

Located on Campus Drive East between the Recreation Center (Rec) and Bryce Lawn Apartments, the Project serves the overall east-central campus area as there is a high density of students in the area and in the surrounding housing complexes and fraternity houses along University Boulevard, Bryce Lawn Drive and Jefferson Avenue. The Project also provides quick access for users of the Rec Fields during other inclement weather events.

 

View Progress Photos!
Renderings Array
Budget 9793825
Banner Fund Number 90944
Project Accountant Cindy Fowler
Funding Source(s) Array
Construction Dashboard Link
Link to Awarded Contracts Dashboard https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard
View Bid Tab https://constructionpublicinfo.ua.edu/certified-bid-tabs/
Link to eCORAF https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList
Link to ePayApp https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard
ePIRPAF Link
Stage 1 BOT Submittal(s) Array
Stage 2 BOT Submittal(s) Array
Stage 3 BOT Submittal(s) Array
Stage 4 BOT Submittal(s) Array
BOT Site
RFQ Documents
Advertisement for Bids
Bid Tabulations Array
Link to Bid Site https://constructionpublicinfo.ua.edu/bids/
Consultant Agreements https://constructionpublicinfo.ua.edu/agreements/
Design Guidelines https://constructionpublicinfo.ua.edu/design-guidelines/
Front End Documents https://constructionpublicinfo.ua.edu/front-end-documents/
Instructions Link https://constructionpublicinfo.ua.edu/public-forms/
360 Embed Code
BOT Stage Array