EV Bus and Charging Infrastructure
- UA Transportation Maintenance Facility, USC Campus
Use
Utilities & Infrastructure
Status
Construction Type
New Construction
Current Phase
Programming
College or Division
Other
CA Filing Code
TRN-23-3219
Project GSF
N/A
The EV Bus and Charging Infrastructure Project will purchase eight (8) electric buses and purchase and install electric distribution infrastructure and charging equipment to support new electric bus charging, assisting in modernizing the campus Crimson Ride bus fleet. This modernization is a foundational stage in the UA Transportation department’s “Zero-Emission Fleet Transition Plan”.
These electric bus chargers will be located at the Transportation Maintenance Facility, adjacent to the existing bus parking area on the University Services Campus for overnight fleet charging.
The new electric vehicle charging system and the electric bus fleet will also be utilized by the Alabama Mobility and Power (AMP) Center in multiple electric vehicle Research and Development and workforce training initiatives.
BOT Budget
$9,600,709
Funding Sources
-
Grant Funds :
$7,890,065 -
University Central Reserves :
$1,530,644 -
Center for Advanced Vehicle Technologies :
$180,000
STAGE | PACKAGE INFORMATION |
---|---|
Stage 1 |
|
Stage 2 |
|
Stage 3 |
|
Stage 4 |
|
DATA LABEL | DATA VALUE |
---|---|
Category | Utilities & Infrastructure |
College/Division | Other |
Status | Active |
Construction Phase | Programming |
Construction Type | New Construction |
GSF | N/A |
Street Address | UA Transportation Maintenance Facility, USC Campus |
Zone | |
Project Number | TRN-23-3219 |
Architect | |
Project Manager | |
Project Admin | |
Field Coordinator | |
General Contractor | |
Interior Designer | |
Bid Date | |
Construction Start | |
Scheduled Construction End | |
COSC Date | |
Year End Inspection | |
Fundraising Site | |
SharePoint Active Project Site Link | |
AiM Link | https://fmax.fa.ua.edu/fmax/screen/PROJECT_VIEW?project=XXXXX |
Campus Map Link | |
BIR Building Link | https://bama365.sharepoint.com/sites/98C3D/default.aspx |
Closeout Documents Link | |
View Warranty Documents | |
Project Summary |
The EV Bus and Charging Infrastructure Project will purchase eight (8) electric buses and purchase and install electric distribution infrastructure and charging equipment to support new electric bus charging, assisting in modernizing the campus Crimson Ride bus fleet. This modernization is a foundational stage in the UA Transportation department’s “Zero-Emission Fleet Transition Plan”. These electric bus chargers will be located at the Transportation Maintenance Facility, adjacent to the existing bus parking area on the University Services Campus for overnight fleet charging. The new electric vehicle charging system and the electric bus fleet will also be utilized by the Alabama Mobility and Power (AMP) Center in multiple electric vehicle Research and Development and workforce training initiatives. |
Renderings | |
Budget | 9600709 |
Banner Fund Number | |
Project Accountant | |
Funding Source(s) | |
Construction Dashboard Link | |
Link to Awarded Contracts Dashboard | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard |
View Bid Tab | https://constructionpublicinfo.ua.edu/certified-bid-tabs/ |
Link to eCORAF | https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList |
Link to ePayApp | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard |
ePIRPAF Link | |
Stage 1 BOT Submittal(s) | |
Stage 2 BOT Submittal(s) | |
Stage 3 BOT Submittal(s) | |
Stage 4 BOT Submittal(s) | |
BOT Site | |
RFQ Documents | |
Advertisement for Bids | |
Bid Tabulations | |
Link to Bid Site | https://constructionpublicinfo.ua.edu/bids/ |
Consultant Agreements | https://constructionpublicinfo.ua.edu/agreements/ |
Design Guidelines | https://constructionpublicinfo.ua.edu/design-guidelines/ |
Front End Documents | https://constructionpublicinfo.ua.edu/front-end-documents/ |
Instructions Link | https://constructionpublicinfo.ua.edu/public-forms/ |
360 Embed Code | |
BOT Stage |