H. M. Comer Renovation
- 245 7th Ave, Tuscaloosa, AL 35401
Information at a Glance
Use
Academic
Status
Construction Type
Renovation
Current Phase
Complete
College or Division
College of Engineering
CA Filing Code
245-16-863
Project GSF
70,028
Bid Date
4/6/2017
Construction Start
April 2017
Construction End
August 2018
COSC Date
' 8/1/2018
Project Architect
KPS Group, Inc.
General Contractor
Bailey Harris
Project Manager
Matt Ernst (8-9740)
Field Coordinator
John Chesnut (8-1684)
Interior Designer
Brittany Kyles (8-9001)
Project Admin
TBD
Information at a Glance
BOT Budget
$24,600,000.00
Funding Sources
-
2017 General Revenue Bonds :
$22,600,000 -
University Funds :
$2,000,000
Banner/Project #
90718
Project Accountant
Cindy Fowler (8-5460)
BOT Submissions
STAGE | PACKAGE INFORMATION |
---|---|
Stage 1 |
|
Stage 2 |
|
Stage 3 |
|
Stage 4 |
|
Request for Qualifications
Bid Information
DATA LABEL | DATA VALUE |
---|---|
Category | Academic |
College/Division | College of Engineering |
Status | Closed |
Construction Phase | Complete |
Construction Type | Renovation |
GSF | 70,028 |
Street Address | 245 7th Ave, Tuscaloosa, AL 35401 |
Zone | |
Project Number | 245-16-863 |
Architect | KPS Group, Inc. |
Project Manager | Matt Ernst (8-9740) |
Project Admin | TBD |
Field Coordinator | John Chesnut (8-1684) |
General Contractor | Bailey Harris |
Interior Designer | Brittany Kyles (8-9001) |
Bid Date | 4/6/2017 |
Construction Start | April 2017 |
Scheduled Construction End | August 2018 |
Fundraising Site | |
SharePoint Active Project Site Link | https://uafinancialaffairs.sharepoint.com/sites/7M27T/245-16-863/ |
AiM Link | https://fmax.fa.ua.edu/fmax/screen/PROJECT_VIEW?project=90718 |
Campus Map Link | https://map.concept3d.com/?id=1222#!m/324802 |
BIR Building Link | https://uafinancialaffairs.sharepoint.com/sites/98C3D/Zone1/buildings/245 |
Construction Photos Link | |
Project Summary | |
Renderings | |
Budget | 24600000 |
Banner Fund Number | 90718 |
Project Accountant | Cindy Fowler (8-5460) |
Funding Source(s) | |
ePIRPAF Link | https://everest-sf.fa.ua.edu/Runtime/Form/Project%20Initiation%20Request/?_State=PIR_HISTORY&GUID=07CD9A8A-7034-4E12-8E31-5B5D6FEF1AA7 |
Construction Dashboard Link | https://spd.ua.edu/construction/Awards/Funds?fund=90718&detail=all |
View Bid Tab | https://constructionpublicinfo.ua.edu/wp-content/uploads/Public-Quick-Links/Certified-Bid-Tabs/Renovation-of-H.-M.-Comer-Hall-245-16-863-4-6-17.pdf |
Link to Awarded Contracts Dashboard | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard |
Link to eCORAF | https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList |
Link to ePayApp | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard |
Stage 1 BOT Submittal(s) | |
Stage 2 BOT Submittal(s) | |
Stage 3 BOT Submittal(s) | |
Stage 4 BOT Submittal(s) | |
BOT Site | |
COSC Date | 8/1/2018 |
Year End Inspection | 8/1/2019 |
View Warranty Documents | |
Link to Bid Site | https://constructionpublicinfo.ua.edu/bids/ |
Consultant Agreements | https://constructionpublicinfo.ua.edu/agreements/ |
Design Guidelines | https://constructionpublicinfo.ua.edu/design-guidelines/ |
Front End Documents | https://constructionpublicinfo.ua.edu/front-end-documents/ |
Instructions Link | https://constructionpublicinfo.ua.edu/public-forms/ |
Advertisement for Bids | |
Closeout Documents Link | |
RFQ Documents | |
Bid Tabulations | |
360 Embed Code |