Univ. Blvd. Rose Admin. to 6th Ave. Infrastructure Improvements and Storm Drainage Extension
- University Boulevard from Rose Administration to 6th Avenue
Use
Utilities & Infrastructure
Project Status
Closed
Construction Type
Infrastructure/Utilities
Current Phase
Complete
College or Division
General Campus
Project Number
000-26-4176
Bid Date
February 24, 2026
Construction Start
May 2026
Construction Complete
August 2026
Architect/Engineer
Duncan Coker Associates
General Contractor
Lavender
Project Manager
David Welch
Field Coordinator
Chuck Hinton
Project Admin
Ambria Carter
The proposed University Boulevard Rose Administration to 6th Avenue Infrastructure Improvements and Storm Drainage Extension project (“Project”) will deliver essential upgrades to the storm drainage system along University Boulevard, a primary connector serving as a vital corridor into the academic core of campus. The Project includes a significant expansion of stormsewer coverage. These enhancements are designed to substantially reduce recurring roadway and sidewalk flooding that has historically impeded vehicular movement, pedestrian access, and overall circulation within this key campus corridor.
The Project will also include the removal of existing concrete paving and the installation of new asphalt, creating a smoother, more durable, and visually cohesive roadway consistent with previous phases of University Boulevard improvements. Additionally, new, wider sidewalks will be constructed on the southern side of University Boulevard, improving pedestrian comfort, accessibility, and safety along this heavily traveled route. This project will include exterior security enhancements to the north side of the yard and the entrance to the President’s Mansion.
Enhanced landscaping and hardscaping elements will further improve the aesthetics and functionality of this gateway, supporting the daily movement of students, faculty, staff, and visitors throughout the University’s central academic areas.
BOT Budget
$4,497,229
Funding Sources
-
Institutional Reserves :
$4,497,229
Banner/Project #
91351
Project Accountant
Sonia Wilkins
| STAGE | PACKAGE INFORMATION |
|---|---|
Stage 1 |
|
Stage 2 |
|
Stage 3 |
|
Stage 4 |
|
| DATA LABEL | DATA VALUE |
|---|---|
| Category | Utilities & Infrastructure |
| College/Division | General Campus |
| Status | Closed |
| Construction Phase | Complete |
| Construction Type | Infrastructure/Utilities |
| Street Address | University Boulevard from Rose Administration to 6th Avenue |
| Zone | |
| GSF | |
| Project Number | 000-26-4176 |
| Architect | Duncan Coker Associates |
| General Contractor | Lavender |
| Project Manager | David Welch |
| Project Admin | Ambria Carter |
| Field Coordinator | Chuck Hinton |
| Interior Designer | |
| Bid Date | February 24, 2026 |
| Construction Start | May 2026 |
| Scheduled Construction End | August 2026 |
| COSC Date | |
| Year End Inspection | |
| Fundraising Site | |
| SharePoint Active Project Site Link | |
| AiM Link | https://fmax.fa.ua.edu/fmax/screen/PROJECT_VIEW?project=91351 |
| Campus Map Link | |
| BIR Building Link | https://bama365.sharepoint.com/sites/98C3D/default.aspx |
| Closeout Documents Link | |
| View Warranty Documents | |
| Project Summary |
The proposed University Boulevard Rose Administration to 6th Avenue Infrastructure Improvements and Storm Drainage Extension project (“Project”) will deliver essential upgrades to the storm drainage system along University Boulevard, a primary connector serving as a vital corridor into the academic core of campus. The Project includes a significant expansion of stormsewer coverage. These enhancements are designed to substantially reduce recurring roadway and sidewalk flooding that has historically impeded vehicular movement, pedestrian access, and overall circulation within this key campus corridor. The Project will also include the removal of existing concrete paving and the installation of new asphalt, creating a smoother, more durable, and visually cohesive roadway consistent with previous phases of University Boulevard improvements. Additionally, new, wider sidewalks will be constructed on the southern side of University Boulevard, improving pedestrian comfort, accessibility, and safety along this heavily traveled route. This project will include exterior security enhancements to the north side of the yard and the entrance to the President’s Mansion. Enhanced landscaping and hardscaping elements will further improve the aesthetics and functionality of this gateway, supporting the daily movement of students, faculty, staff, and visitors throughout the University’s central academic areas. |
| Renderings | |
| Budget | 4497229 |
| Banner Fund Number | 91351 |
| Project Accountant | Sonia Wilkins |
| Funding Source(s) | |
| Construction Dashboard Link | |
| Link to Awarded Contracts Dashboard | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard |
| View Bid Tab | https://constructionpublicinfo.ua.edu/certified-bid-tabs/ |
| Link to eCORAF | https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList |
| Link to ePayApp | https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard |
| ePIRPAF Link | |
| Stage 1 BOT Submittal(s) | |
| Stage 2 BOT Submittal(s) | |
| Stage 3 BOT Submittal(s) | |
| Stage 4 BOT Submittal(s) | |
| BOT Site | |
| RFQ Documents | |
| Advertisement for Bids | |
| Bid Tabulations | |
| Link to Bid Site | https://constructionpublicinfo.ua.edu/bids/ |
| Consultant Agreements | https://constructionpublicinfo.ua.edu/agreements/ |
| Design Guidelines | https://constructionpublicinfo.ua.edu/design-guidelines/ |
| Front End Documents | https://constructionpublicinfo.ua.edu/front-end-documents/ |
| Instructions Link | https://constructionpublicinfo.ua.edu/public-forms/ |
| 360 Embed Code | |
| BOT Stage |