Paty Hall Renovation

  • 210 McCorvey Drive, Tuscaloosa, Alabama 35487
Information at a Glance

Use

Residential

Status

Active

Construction Type

Renovation

Current Phase

Complete

College or Division

Division of Student Life

Bed Count

400

CA Filing Code

247-18-1818

Project GSF

90,384

Bid Date

January 10, 2019

Construction Start

February 2019

Construction End

20190801

COSC Date

' July 26, 2019

Project Architect

Ward Scott Architecture

General Contractor

WAR Construction

Project Manager

Steven Mercado (8-4640)

Field Coordinator

Jon Chesnut (8-1684)

Interior Designer

Leah Shepherd (8-8450)

Project Admin

Brittney Fox (8-5577)

Project Summary

The Interior Renovation Package completed on July 26, 2019.

The Exterior Stairwell and Improvements package bid on November 7, 2019 and is scheduled for construction over summer 2020.


Information at a Glance

BOT Budget

$14,370,000.00

Funding Sources

  • Housing and Residential Communities Reserves :
    $14,370,000

Banner/Project #

90845

Project Accountant

Demon Patrick (8-8714)

DATA LABEL DATA VALUE
Category Residential
College/Division Division of Student Life
Bed Count 400
Status Active
Construction Phase Complete
Construction Type Renovation
GSF 90,384
Street Address 210 McCorvey Drive, Tuscaloosa, Alabama 35487
Zone 2
Project Number 247-18-1818
Architect Ward Scott Architecture
Project Manager Steven Mercado (8-4640)
Project Admin Brittney Fox (8-5577)
Field Coordinator Jon Chesnut (8-1684)
General Contractor WAR Construction
Interior Designer Leah Shepherd (8-8450)
Bid Date January 10, 2019
Construction Start February 2019
Scheduled Construction End 20190801
Fundraising Site
SharePoint Active Project Site Link https://uafinancialaffairs.sharepoint.com/sites/7M27T/247-18-1818/SitePages/Home.aspx
AiM Link https://fmax.fa.ua.edu/fmax/screen/PROJECT_VIEW?project=90845
Campus Map Link
BIR Building Link https://uafinancialaffairs.sharepoint.com/sites/98C3D/Zone2/buildings/247
Construction Photos Link https://uafinancialaffairs.sharepoint.com/sites/7M27T/247-18-1818/Project%20Photos/Forms/Thumbnails.aspx?viewid=f5bbcb8c%2D678f%2D4926%2D8fe9%2D9250ef706e52
Project Summary

The Interior Renovation Package completed on July 26, 2019.

The Exterior Stairwell and Improvements package bid on November 7, 2019 and is scheduled for construction over summer 2020.

Renderings
Budget 14370000
Banner Fund Number 90845
Project Accountant Demon Patrick (8-8714)
Funding Source(s)
ePIRPAF Link https://everest-sf.fa.ua.edu/Runtime/Form/Project%20Initiation%20Request/?_State=PIR_HISTORY&GUID=94B72EB1-4D55-4180-8847-0744D272C89D
Construction Dashboard Link https://spd.ua.edu/construction/Awards/Funds?fund=90845&detail=all
View Bid Tab https://constructionpublicinfo.ua.edu/wp-content/uploads/Public-Quick-Links/Certified-Bid-Tabs/Paty-Residence-Hall-Renovation-247-18-1818-1-10-19.pdf
Link to eCORAF https://everest-sf.fa.ua.edu/Runtime/Form/CORAFList
Link to ePayApp https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+PayApp+Dashboard
Stage 1 BOT Submittal(s)
Stage 2 BOT Submittal(s)
Stage 3 BOT Submittal(s)
Stage 4 BOT Submittal(s)
BOT Site
COSC Date July 26, 2019
Year End Inspection July 26, 2020
View Warranty Documents
Link to Awarded Contracts Dashboard https://everest-sf.fa.ua.edu/Runtime/Form/Awarded+Contracts+Dashboard
Link to Bid Site https://constructionpublicinfo.ua.edu/bids/
Consultant Agreements https://constructionpublicinfo.ua.edu/agreements/
Design Guidelines https://constructionpublicinfo.ua.edu/design-guidelines/
Front End Documents https://constructionpublicinfo.ua.edu/front-end-documents/
Instructions Link https://constructionpublicinfo.ua.edu/public-forms/
Advertisement for Bids
Closeout Documents Link
RFQ Documents
Bid Tabulations
360 Embed Code

The renovation upgraded Paty Hall and was completed in August of 2019. The exterior and stairwell improvement work will be completed over Summer 2020.